Missed deadline Promise · Medium confidence

PMAY missed its 2022 deadline: both the rural and urban schemes were extended, and completions were below sanctions and targets at the extended dates found.

Test case in Suite B · score 0.25

English · ParaphrasedEvery family to have a pucca house (with electricity access) by 2022, the 75th year of independence (paraphrase of the Housing for All / New India 2022 vision).

Paraphrased from news reports; not a verbatim quote.

Speaker
Narendra Modi
Party
BJP
Office
Prime Minister
Venue
Independence Day address, Red Fort, Delhi
Date
2017-08-15
Deadline
2022-12-31
Topics
housing, infrastructure
Researched by
claude-sonnet

Transcript / text sources

Evidence

TypePublisherTitleDateKey figure
ParliamentLok Sabha / Ministry of Rural DevelopmentPMAY-G completions as of 3 Aug 2026 (reported by NBM&CW)2026-08-123.12 crore completed vs 4.18 crore allocated and 3.91 crore sanctioned; 79 lakh still under construction
ParliamentLok Sabha / MoHUACabinet extends PMAY-urban deadline till December 2024 (Housing.com)2022-08-10PMAY-U extended from 2022 to 31 Dec 2024; later reply (Dec 2023): 118.63 lakh sanctioned, 78.27 lakh completed as of 4 Dec 2023
NewsHousing.comNo plan yet to extend PMAY-G beyond March 2024: Govt2023-08PMAY-G target 2.95 crore houses; scheme continued beyond March 2021 till March 2024; 2.10 crore completed per Lok Sabha reply of 8 Dec 2022
NewsNBM&CW / ParliamentPMAY-U figures as of 13 July 2026 (The Aarch News)2026-07127.68 lakh sanctioned (incl. 16.20 lakh under PMAY-U 2.0), 99.07 lakh completed; scheme now to 30 Sept 2026

The data

PMAY-G houses completed (cumulative) (houses (number)) — Source: Ministry of Rural Development (Lok Sabha replies, via news reports), PMAY-G progress. Target: 29500000 (PMAY-G cumulative target of 2.95 crore houses (original deadline 2022, extended to March 2024)). Rounded crore figures as reported in Lok Sabha replies (2.10 crore, about 2.55 crore, 3.12 crore). The first two come from search summaries, not the replies themselves. Original target 2.95 crore by 2022, extended to March 2024, then new phase to 2029.

Government's response

Cabinet approval of PMAY-G continuation 2024-25 to 2028-29

Government extended the schemes (Cabinet, Aug 2022 for PMAY-U; 9 Aug 2024 for 2 crore more PMAY-G houses to 2028-29), citing pandemic delays and a revised demand count; it says over 3 crore rural and 99 lakh urban houses have been delivered.

Analysis

The Housing for All by 2022 aim was set in the President's address (June 2014) and the 2014-15 Budget, and repeated by the PM, including in 2017's 'New India 2022' framing. PMAY-G's cumulative target was 2.95 crore houses; PMAY-U targeted about 1.2 crore.

In December 2022 about 2.10 crore PMAY-G houses were complete; in February 2024 about 2.55 crore. PMAY-U's deadline was extended to December 2024 and then further. Completions have since risen, but the schemes continue and targets have been enlarged.

The housing shortfall depends on how demand is counted; this entry only assesses the 2022 deadline for the scheme's own targets.

Confidence in verdict & review

Confidence in verdict
Medium
Review status
draft
Last reviewed
2026-10-17

Notes

Speech wording not verified; date set to the 2017 Red Fort speech per a Deccan Herald opinion piece that was not fetched. A Delhi rally statement (Deccan Herald, 'pucca houses to all poor families by 2022') could not be opened (403) and its date is unknown. Several figures (2.10 crore Dec 2022; 2.55 crore Feb 2024; 78.27 lakh PMAY-U) come from search-result summaries of Lok Sabha replies/news, not the PDFs (eparlib fetch failed). Needs human check against the originals. The 'Housing for All' commitment originates with the President's address June 2014.

Human review Draft

No human review yet.